La Pura

Progress Update

Project Construction Partner

La Pura is developed and supervised by reputable partners with extensive experience in high-end real estate construction. Quality and handover timelines are strictly ensured.

Main Contractor: Centralcons

Supervision Consultant: Artelia

Property Management & Consultancy: CBRE

Project Completion Guarantee: VPBank
(Funds disbursed directly to Centralcons)

Expected Completion: December 2026

La Pura Construction Progress (October 2025)

  • La Pura is taking shape day by day — ready to welcome its future residents. ☀️

    October marks another month of steady progress across the development:

    🏗 Zenia Towers:

    • Zenia 1 has reached the 13th floor

    • Zenia 2 has topped out at the 16th floor

    🏗 Risa Towers:

    • Risa 1 has risen to the 14th floor

    • Risa 2 has achieved the 18th floor milestone

    🏗 Lightweight concrete wall installation is now being carried out simultaneously across multiple levels.

    🚧 Notably, the National Highway 13 (QL13) expansion to 60 meters is steadily taking shape — further enhancing regional connectivity and accessibility.

    At the same time, the on-site Sales Gallery is under continuous construction, soon ready to welcome guests for visits and immersive project experiences.

La Pura Construction Progress (May 2025)

  • As of March 2025, La Pura’s construction is progressing on schedule:

    • Site leveling and foundation work: Completed

    • Basement structure: Completed

    • Podium construction: Underway (80% completed)

    • Tower blocks: Construction started on lower floors

    • Overall progress: Approximately 40% completed

    • Estimated handover: December 2026

Artelia Vietnam Conducts Comprehensive Quality Inspection of La Pura Project

On April 28th, Artelia Vietnam – the independent international consulting, engineering, and project management group from France – collaborated with the main contractor Central to conduct a comprehensive quality inspection of the La Pura project.

Following a detailed inspection and careful comparison of test results with the approved design documents, Artelia’s supervisory team concluded that the quality of the concrete and reinforced steel structures at La Pura fully complies with all technical specifications, construction standards and regulations, as well as the requirements outlined in the approved design documents.

La Pura is making steady progress towards completion, ready to become a new symbol of wellness-inspired living in the heart of the city.

La Pura Construction Progress (March 2025)

Project Kick-Off Ceremony: The Healing City (April 17, 2025)

Get Exclusive Pricing &